Reference: Scrum points
2022-02-11UPDATE [2023]: Understanding and perceptions around Agile and Scrum practices have been so convoluted that I no longer want to be associated with them. The agile manifesto is still good. However, the attempted applications of it in larger organizations and consultancies? …not so much.
There are my notes regarding Scrum processes for software development. I’ve written some variant of these notes for multiple companies, primarily to establish guidelines around point estimates for teams that are new to Scrum.
I am not an expert on Agile or Scrum practices. Every team and project is different. I believe that software dev teams should strive for self-management and keep ceremony to a minimum. But, it takes time for a team to learn to work together, and guidelines like these can help get started.
Contents
Point Guidelines
Reasons for estimating with points:
- As developers, there should be a general agreement on the level of effort that will be needed to complete a given story. Agreement helps with estimation accuracy and making sure the story is sufficiently defined.
- As managers and planners, point related metrics will become useful for estimating and prioritizing future work.
Point values, velocity, & capacity are relative to a team and have little meaning outside that team. I am providing my suggestions here as a starting point for point values, but these are only suggestions.
I like using the Fibonacci sequence (or a doubling sequence) because it helps to remember that the point values are completely relative. Point values should be representation of complexity and effort for the team to complete. They do not always map to time-to-complete, but in practice, that’s usually the most useful way to estimate.
These guidelines assume 2-week sprints.
1 Point
A story or task that needs to be tracked, but it will only take a minute or two for someone to complete. No risks. No questions.
2 Points
Not 1 and not 3. Should only take a few minutes. Many teams don’t bother using 2 point values when using Fibonacci scale.
3 Points
Will usually take someone an hour or so. No risks. No questions.
5 points
Will usually take someone a few hours or full day to complete. Might have to ping someone else a few times. Little risk. No real questions.
8 points
Probably take a few days, or even a full week to complete. Might involve more than person. Maybe some minor risks once work is started. Not too many questions.
13 points
Probably take at least a week to complete. Might involve more than one person. Probably has risks and questions that might develop after work begins.
21 points
Expect it will take the entire sprint. Might involve more than one person. Probably has risks and more questions once work begins. However, this could also simply be an effort-intensive development task that will need the full sprint.
21+
Generally unused. If team can not estimate a story at 21 or less, then the story should be researched and/or broken down further before being moved in to the sprint.
{SPIKE}
A story/task tracking the effort needed to better understand something before it can be estimated. Said another way, we don’t know what we don’t know. This usually involves research or cross team commu-nications. Team might try assigning point values based on a suggested time box.
{BUG}
Sometimes the effort needed to address and fix a reported bug can be estimated, and sometimes it cannot. At least, not until the underlying bug cause has been determined. Sometimes bugs are dependent on waiting for customer feedback and follow-ups, which can also generally not be estimated.
Related Thoughts
Cross Product/Projects
Scrum is not great for working across multiple projects. Generally, scrum expects a cross-functional team (and associated sprint board) to be working on a single project at a time. Reality is often different. But, I think that is important to remember than when figuring out how best to apply Scrum based practices and tools in a team environment.
Context Switching
Related to previous point, context switching often has a significant cost. A developer being asked to work across multiple projects in a sprint will not be able to complete the same amount of work as when they are focused on a single project. That is true for the team as a whole too. That should be considered in any future capacity planning.
Spikes
It will often be the case, especially early on, that a team will have stories that can not be accurately estimated because they don’t know what they don’t know. That makes it hard to assign points and track capacity/velocity. Teams sometimes call stories of this sort “spikes”. It has been recommended to me that when doing this, the spike be time boxed. For example, do R&D for ~3 days and then report status and results so team can decide how best to continue.
Tools
It is my belief that the available tools for scrum team management aren’t great. They often add overhead and friction to teams that need to be quickly adapting as projects continue to move forward and new information is gained. I try and always remember that the goal with these processes is to be constantly moving forward, supporting management’s need for forward-looking planning, and trying not to stress too much. The goal should never be the process itself.
The limitations of the tools should be taken in to consideration when figuring how best to apply processes. There can be a natural tension between wanting to do the work someone knows needs to be done, and tracking that accurately according to the work someone said was going to be done.
Point Accuracy
Assigning points to stories should be done by multiple developers looking at a story and providing their best guess as to the complexity/required-effort for the team to complete the story. The estimate should be as if that story would be the only focus within a sprint (even if that is almost never the case). Coming up with point values should not take a significant amount of time and no one should expect point values to be overly accurate. The nature of software development work makes consistently accurate estimates almost impossible.
When assigning points, playing poker should lead to more discussion only if the point ranges are exceptionally wide. That could indicate the story is not clear. Otherwise, assign the average and quickly move on. What is ultimately important to those concerned with capacity/velocity/burndowns is point averages over time. Generally, a team’s current capacity is calculated as the average of points completed over the last X sprints.
Meeting and Ceremony Control
Everyone on team should strive to keep the purpose and context of various meetings and ceremonies in mind. Otherwise, every meeting has potential of running over its allotted time and doing so repeatedly will cause compounding problems. Most sprint planning related work should be done in backlog refinement. Subsequent meetings are then mostly painless. …admittedly, I’ve rarely seen this done well. One reason is that in a fast-paced team, by the time a story moves from backlog in to a sprint, the available information and requirements have already changed. But, that’s what being agile is about…and I try to remind myself it’s only the processes that are having problems keeping up.
Estimate High
Prefer to over estimate story points, at least initially. For multiple reasons, it is better for a team to end a sprint with all stories completed early (uncommon) than it is to end a sprint with stories still-in-progress(very common) or not started.
At higher levels, planners should generally aim for sprint point allocation at ~75% of average capacity. Developers are asked to dedicate ~80% of time to project tasks, and leave ~20% for self-development and other important things, like breathing. That doesn’t show up in points (which are relative), but should be kept in mind when considering what can actually get done in a sprint.
Story Format
User stories should almost always use the format:
- “As a [persona], I [want to], [so that].”
If it’s not written out explicitly, it should be easily inferred. Many teams do not do this, and I’ve seen that it often leads to confusion due to different contexts and expectations. This is especially true for teams that are new to Scrum.
A personal practice is to use this even for technical enablement stories. For example:
- “As a DevOp, I want a CI/CD pipeline into Alpha, so that I have a shared environment for automated builds and unit tests.”
Stories are generally not meant to be Tasks, To Do Items, or Checklists. Generally, a story should describe the requirement, enhancement, feature, or bug. The team estimates what it would take to resolve the story. A sprint board is not meant to be a list of tasks to be done for that sprint. It’s a list of stories that will be resolved in that sprint, but the actual work (tasks) it takes to do so does not always need to be part of sprint planning beyond understanding things well enough to be able to roughly estimate effort required. (Sometimes that does mean developers need to think through all the required tasks first, but not always.)
Change is Inevitable
Unexpected change is inevitable in software development. Sometimes that is due to external requirements changing, sometimes it due to new information, and sometimes it’s simply due to unforeseen events. Most often it’s because requirements couldn’t be fully understood until work had progressed to some point. A software dev team that expects, and can react quickly, to change and new information is a good thing.
Processes and tools can cause friction when there is a lot of change. Teams should be frequently assessing and weighing the pros and cons of any methodology being used. That assessment should be made from the view point of all constituents though. Developers sometimes forget that methodology/process/estimating/planning is important to higher level business concerns. Management sometimes forget that software development has non-obvious complexities that can make it hard to estimate or handle changes.
Common Questions
Below are some common questions to be answered when a team adopts a scum approach. Scrum has answers for all of these when in larger teams and there are dedicated people assigned to all roles. But in smaller teams, these tend to be useful questions. It’s easy to answer “Product Owner” for most of them, but in my experience, the more a product owner can delegate, the better.
Q) Who can/should create new stories in the backlog?
Q) Who can/should prioritize new stories in the backlog?
Q) How will new stories be brought to the attention of those prioritizing?
Q) What is the agreed upon hierarchy for epics, stories, tasks, and subtasks?
Epic - Estimated with t-shirt sizes
Story - Estimated with points
Tasks - Not estimated. Used to show todos/acceptance-criterias/requirements, and sometimes to show progress within a story. Sometimes useful for handling finer-grained pre-requisite relationships and blockers
Subtasks - Not used for any planning purposes.
Q) Can the team add stories/bugs to an active sprint? Should the team modify sprint to reflect actual work?
(My recommendation is that changes to active sprint be made infrequently if possible, with high priority bugs being an
exception.)
(However, a team should avoid the mindset of “We know it would be best if this was worked on immediately, but it’s not in the current sprint, therefore we’ll have to wait.” A team should never let the process get in the way of doing the right thing. However, developers in more formal teams should also recognize that sometimes the coach/manager has non-obvious reasons for certain priorities. As always… communication is key.)
Q) Can we change point values of an active sprint story when new information becomes available?
(My recommendation is that this is done rarely.)
Q) When a sprint ends and story is not yet complete, will we move it forward to the next sprint and keep the point value
the same?
(My recommendation is, yes, unless new information became available that changed the story significantly. Averages over multiple sprints are what matter. And when there are significant changes that will extend beyond a sprint, it’s generally better to break in to new story (or stories).)